[VAWT] First practical tests

The first practical tests have commenced! The windmill below is built within this Bachelors Thesis:  We had worked in small subgroups, where I had focused on calculations, software and electronics. Some other guys had done the mechanical design and therefore I didnt't see the turbine first until the day all parts were to be assembled. What I hadn't realised before is that the turbine is huge! It measures some above 3 meter in height. Here is a rather crappy first movie of over first test run:  Turbine control is done via electronic switching by using PWM. A Maximum Power Point tracking algorithm is tried here. Among other things wind and electrical output (voltage and current) are measured that can be used to evaluate system performance. This can be used for estimating turbine output. The current measurement was bit of a challenge to design as it had to work over the unusually large range 0,5- 60 amps. The measurement is split up in to ranges in hardware in this